Swanson Group Will Rebuild Oregon Plywood Mill
Plans are to have the new mill finished and ready to start up by mid 2016. The new plant will employ 190 and operate similar to the old facility in terms of capacity and product lines, with a few twists.
According to Swanson, approval for the new building was in mid February. Most of the equipment purchases will take place between now and May, and the new building is expected to be complete and ready by fall 2015.
While Swanson personnel are still looking at equipment types and suppliers and combinations of new and used equipment, Swanson says the mill will utilize a state-of-the-art triple-spindle peeling system with sheet and random stacking; two dryers, one handling wides and the other randoms, feeding to respective stacking systems; and a layup line and related systems that enable more overlay production.
Latest News
Uniboard Modernization On Track At Val-d’Or
Uniboard reports its $350 million particleboard plant modernization program is going as planned at Val-d’Or, Quebec; originally announced in June 2022, this is the third phase of its modernization for its particleboard and TFL mill. More than $100 million was invested in Phase 1 and Phase 2, which were…
Jim Herold Retires From Rainier Veneer
Rainier Veneer, Inc., Spanaway, Wash., announced that Plant Manager Jim Herold retired the first of June after 25 years as manager. Previously Herold worked at Roseburg Forest Products where he was plant manager of the Dillard plywood mill. He began his career at RFP after graduating from Oregon State University in 1974…
West Fraser Announces Senior Leadership Transition Plan
Hank Ketcham, Chairman of West Fraser’s Board of Directors, announced that Ray Ferris, current West Fraser President and Chief Executive Officer, plans to retire on December 31, 2023. Ferris has been with West Fraser for over 26 years in increasingly senior positions culminating in his appointment as President and Chief Operating Officer in 2018 and as a director of the Company in 2019…
Andritz Selected To Supply Roseburg Complete MDF Line
Andritz has received an order from Roseburg Forest Products Co. to supply a complete fiber preparation line for medium density fiberboard (MDF) production to its new mill in Dillard, Ore. This investment is part of Roseburg’s major program to upgrade…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!