Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
U.S. Forest Service Celebrates CLT During Forest Products Week
From October 21-27, 2018, we celebrate the value of America’s forests and recognize how vital they are to our well-being and national prosperity...
Arauco-Grayling Is Paving The Way
As of the end of August, Arauco reported 1,526,355 total project hours completed since April 2017 at its particleboard plant under construction in...
Boise Cascade Selling Two Sawmills, P’Board Operations In Oregon To Woodgrain
Boise Cascade Company has entered into an agreement with Woodgrain Millwork to sell its northeast Oregon lumber mills in Pilot Rock and La Grande...
Canadian Timber Building Could Be A Trendsetter
Construction is underway in downtown Toronto on a multi-story mixed-use project that incorporates an innovative combination of glulam and...
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!