Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
West Fraser Enhances Williams Lake Plywood With New Westmill Dryer
Westmill supplied a new steam-heated, four-deck jet veneer dryer to replace Dryer #1 at the West Fraser Williams Lake plywood mill in BC. The original Coe M-72 dryer had been in service since the mid-1970s,…
Medite Smartply Taps Dieffenbacher For 55 MW Biomass Energy Plant
Medite Smartply will replace natural gas with biomass for energy production using a Dieffenbacher 55 MW biomass firing system at its MDF plant in Clonmel, Ireland. Dieffenbacher Energy will be responsible for the engineering, equipment…
Trump Says Canada Should ‘Cough’ Up More Tariffs For The Bad Air
President Trump on July 17 condemned Canada, and specifically Ottawa, for improper forest management, leading to the recent increase in forest fires and to the encroachment of smoke and polluted air into the U.S. “We…
Rayonier Appoints Ryan Daniels Senior Vice President, Wood Products
Rayonier Inc. has announced the appointment of Ryan Daniels as Senior Vice President, Wood Products, effective immediately. Daniels has served as Interim Senior Vice President, Wood Products, since March 20, 2026. Following the conclusion of…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!