Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
FPIC At Louisiana Tech Receives Donation
Martin Sustainable Resources LLC of Alexandria, La. has donated $1 million to Louisiana Tech as a leadership gift toward construction of the University’s new Forest Products Innovation Center (FPIC), with the assurance of another $1…
Kadant Completes Key Knife Acquisition
Kadant Inc. has completed its previously announced acquisition of Key Knife, Inc. and some of its affiliates for approximately $156 million in cash, subject to certain customary adjustments. The acquisition was financed primarily through borrowings…
PELICE 2024 Continues To Light Up Scoreboard With New Presentations
Organizers of the ninth Panel & Engineered Lumber International Conference & Expo announced that attendee registration is open for the event, which will be held March 14-15, 2024 at the Omni Atlanta Hotel at Centennial…
Kronospan Completes Simsboro Particleboard Purchase
Kronospan, a producer of wood panel products, has announced the closing of its purchase of Roseburg’s Simsboro, La., particleboard facility following the expiration of the required regulatory review period. Ownership of the plant has been…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!