Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
BC Mills Under Dust Inspection
WorkSafeBC officers have begun another round of inspections as part of the ongoing combustible dust initiative to focus sawmills and other wood processors on keeping work sites safe. During the inspections WorkSafeBC officers examine dust…
Plum Creek Adds To Timber Base
Plum Creek Timber Co., Inc. has signed a $1.1 billion agreement to acquire approximately 501,000 acres of industrial timberlands, associated wind and mineral assets, and an interest in approximately 109,000 acres of high-value rural and…
Ellis Martin Led Family Business
Ellis Spencer Martin, one of the family members responsible for the growth of Roy O. Martin Lumber and Martin Timber Co., died October 18, 2013 in Alexandria, La. He was 96. The eldest son of…
Knokey Behind Many Plywood Developments
Gene (Eugene Rae) Knokey, the technical inspiration and motivating force behind the development of much of the plywood process machinery still considered today the standard of the industry, died August 22, 2013 in Anacortes, Wash.…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!