Labor, Materials Issues Cause Project Delays

The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.

In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.

The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.

Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.

Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.

According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.

 

Latest News

Bud Calvert Dies At 97

Bud Calvert Dies At 97 Harry (Bud) Calvert, a major participant in the plywood industry and principal of Calvert Manufacturing, died May 20....

Roseburg Promotes Grady Mulbery

Allyn Ford, president and CEO of Oregon-based Roseburg Forest Products, announced the promotion of Grady Mulbery to Vice President of Manufacturing...

Sawmill Project Plans New Design

Multiple fingerjointing lines and edge gluing production will be part of a $250 million wood processing complex to be built in Winslow, Ariz. by...

Soy Fiber Based Plant Starts Up

Soy Fiber Based Plant Starts UpAgristrand Mankato, LLC reports that production has commenced at its 160,000 sq. ft. manufacturing facility in...

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!