Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
B.C. Particleboard Plant Revamps For Pellet Production
A Northern Engineered Wood Products (NEWPRO) particleboard facility is filing a permit amendment to become a wood pellet manufacturing plant. Particleboard production has been halted at the Smithers, BC, plant since January 2014. Although not…
CLT Manufacturing To Increase In Pacific Northwest
Oregon and southwest Washington make up one of 12 new regions accepted into the Investing in Manufacturing Communities Partnership initiative. The program is a federal effort to increase domestic manufacturing by “supporting the development of…
Luxor Begins Manufacturing Architectural Wood Products For Woodtone Industries
Luxor Industrial Corporation is pleased to announce that it has commenced manufacturing architectural wood products for Woodtone Industries based in Chilliwack, British Columbia. Luxor has received orders for 788 units of knee-braces and 400 units…
APA Outlook: Industry Expects Increasing Demand For Engineered Wood Products
APA – The Engineered Wood Association has released its 2015 Market Outlook report. Similar to 2014, extremely harsh weather caused home building to stall in the eastern half of the U.S. during the first quarter…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!