Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
Louisiana-Pacific Adds Production Line At Alabama OSB Mill
Louisiana-Pacific Corp. recently broke ground on a project that will add a FlameBlock Fire-Rated OSB Sheathing line at its Clarke County oriented strand board (OSB) mill. A new facility will be constructed to house the…
Tall Wood Building Committee Will Work On 2021 Global Building Codes
The American Wood Council says the International Code Council (ICC) Board of Directors approval of the formation of a Tall Wood Building Ad Hoc Committee. The committee will be made up of stakeholders, code officials…
Kronotex Announces South Carolina Laminate Flooring, Panel Mill Expansion
KronotexUSA and its parent firm Swiss Krono Group will invest $230 million to build a high-density fiberboard mill and expand the company’s laminate flooring production in Barnwell, South Carolina, a move which will create 105…
World’s Tallest Timber Tower Under Construction In Canada
When complete in 2017, the 18-storey (53m) tower, called Brock Commons, will house hundreds of students at the University of British Columbia (UBC). Unless overtaken by other ambitious timber towers now at design or proposal…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!