Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
Competition Drives Oregon Mill Investments
To be competitive in the wood products industry, companies must stay on the cutting edge. But to get to the forefront, wood products companies must invest in their production facilities to increase automation and efficiency,…
China Plywood Dumping Gets Third Review By International Trade Commission
The United States International Trade Commission says there is a “reasonable indication that a U.S. industry is materially injured by reason of imports of hardwood plywood from China that are allegedly subsidized and sold in…
Portland State University Tests CLT’s Seismic Strength
When the 12-story Framework building planned at Portland’s Northwest 10th Avenue and Glisan Street is complete, it may look to passers-by like any other Pearl District condo tower. But it will hold a special distinction…
New OSB Mill Still On Schedule
Work continues in Corrigan, Texas on a new oriented strandboard (OSB) manufacturing plant, the first such facility in the Lone Star State for RoyOMartin. Due to open in fall 2017, the plant represents a $280…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!