CalPlant I Nears The Finish (Or Starting) Line
One of the many intriguing tales to emerge from the Panel & Engineered Lumber International Conference & Expo held March 12-13 at the Omni Hotel in Atlanta was the plight of CalPlant I, the new rice straw-based medium density fiberboard plant entering startup in Willows, Calif. Co-founder and CEO Jerry Uhland told the story of the long and winding road, and the roadblocks therein, to reach the financial and physical realization of the plant, which is why his talk was entitled, 20 Years, 8 Months and 17 Days…But Who’s Counting.
Uhland told of the challenge California rice farmers faced with how to dispose of their post harvest rice straw. Controlled burns had been the primary means, but diminishing air quality prompted a legislative ban in 1991 on open field burning of rice fields, phasing out burning over a 10-year period. Flooding fields to decompose rice straw became the most valuable option but drained a precious resource in a drought prone region.
CalAg was founded in 1996 by longtime California rice industry veterans Jim Boyd and his family and Uhland to address the challenges to rice growers and propose a possible solution. Their trial work on rice straw-based MDF began and the first successful MDF trial was in 1997 at the BioComposites Centre in Bangor, Wales.
Thus began the long and winding road of working with equipment suppliers while trying to get the project funded. Uhland referred to the first three funding efforts that fell short as “Capital Raising Take I, II and III.” Finally in 2017 it came together through bond orders and allocations, resulting in a $315 million financing.
The German-based equipment supplier Siempelkamp had become a crucial partner by then, and the project began construction immediately after funding closed. Today there’s a 325,000 square foot facility on site nearly ready to produce 140MMSF annually of MDF.
Commissioning of some units of operation commenced prior to Siempelkamp departing for Germany mid-March during COVID-19. Siempelkamp engaged a U.S.-based sub to continue load and no-load testing of the production line (i.e. turning the press, load testing post-press processes—CalPlant purchased 8×16 wood-based MDF to test stacking, intermediate storage, sanding, sawing, etc.). Siempelkamp will need approximately five weeks once they return to produce the first board, Uhland estimates.
For additional coverage of Uhland’s presentation at PELICE, and other presentations, see the May 2020 issue of Panel World.
RELATED ARTICLES
CALPLANT I GEARS UP FOR FIRST BOARD
Latest News
Structural EWP Exempt From New EPA Formaldehyde Regulations
The U.S. Environmental Protection Agency’s (EPA) new federal formaldehyde emissions regulations took effect on June 1st, 2018. As of this date all...
Chicago McDonald’s Shows Off Its Cross-Laminated Timber Design
A far cry from the kitschy memorabilia of the Rock ’n’ Roll-themed building it replaces, the essentially all-new design of River North’s flagship...
Half The Fun Is Getting There
This spring I had the opportunity to hop across the pond, and visit Ireland for the first time. An avid Ed Sheeran fan (yeah, I know, but I’m a woman in my early thirties, what do you expect?), I was very excited to visit the countryside he sings about in a few of his…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!