CalPlant I Nears The Finish (Or Starting) Line
One of the many intriguing tales to emerge from the Panel & Engineered Lumber International Conference & Expo held March 12-13 at the Omni Hotel in Atlanta was the plight of CalPlant I, the new rice straw-based medium density fiberboard plant entering startup in Willows, Calif. Co-founder and CEO Jerry Uhland told the story of the long and winding road, and the roadblocks therein, to reach the financial and physical realization of the plant, which is why his talk was entitled, 20 Years, 8 Months and 17 Days…But Who’s Counting.
Uhland told of the challenge California rice farmers faced with how to dispose of their post harvest rice straw. Controlled burns had been the primary means, but diminishing air quality prompted a legislative ban in 1991 on open field burning of rice fields, phasing out burning over a 10-year period. Flooding fields to decompose rice straw became the most valuable option but drained a precious resource in a drought prone region.
CalAg was founded in 1996 by longtime California rice industry veterans Jim Boyd and his family and Uhland to address the challenges to rice growers and propose a possible solution. Their trial work on rice straw-based MDF began and the first successful MDF trial was in 1997 at the BioComposites Centre in Bangor, Wales.
Thus began the long and winding road of working with equipment suppliers while trying to get the project funded. Uhland referred to the first three funding efforts that fell short as “Capital Raising Take I, II and III.” Finally in 2017 it came together through bond orders and allocations, resulting in a $315 million financing.
The German-based equipment supplier Siempelkamp had become a crucial partner by then, and the project began construction immediately after funding closed. Today there’s a 325,000 square foot facility on site nearly ready to produce 140MMSF annually of MDF.
Commissioning of some units of operation commenced prior to Siempelkamp departing for Germany mid-March during COVID-19. Siempelkamp engaged a U.S.-based sub to continue load and no-load testing of the production line (i.e. turning the press, load testing post-press processes—CalPlant purchased 8×16 wood-based MDF to test stacking, intermediate storage, sanding, sawing, etc.). Siempelkamp will need approximately five weeks once they return to produce the first board, Uhland estimates.
For additional coverage of Uhland’s presentation at PELICE, and other presentations, see the May 2020 issue of Panel World.
RELATED ARTICLES
CALPLANT I GEARS UP FOR FIRST BOARD
Latest News
Cross-Laminated Timber As A Forest Management Strategy
The state legislature earlier this year called on the Washington State Building Code Council (WSBCC) to adopt rules for cross-laminated timber (CLT)...
RoyOMartin Announces $8 Million Upgrade, New Jobs At Louisiana Plywood Facility
Gov. John Bel Edwards and RoyOMartin President and CEO Roy O. Martin III announced the company will invest $8 million at its Chopin plywood and...
Longtime Boise Cascade Manager Steve Stoler Retires
Steve Stoler will retire from his position as particleboard sales and marketing manager at Boise Cascade this August, marking the end of a 39-year...
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!